Marine equipment overhaul

Major overhauls of Caterpillar C32 generator sets for the Mat Sinking Unit

In-frame major overhauls of four Caterpillar C32 marine generator set engines aboard Mooring Barge 7403 and Matboat 4801, two working vessels of the Corps’ Mat Sinking Unit at Vicksburg Harbor.

What Cresco handled

  • Caterpillar-authorized dealer as overhaul subcontractor
  • OEM parts and factory-trained technicians
  • Vessel access and work scheduling with district staff
  • Testing, acceptance and closeout documentation

Outcome

All four engines overhauled, accepted and closed out by the Vicksburg District.

02 / 10
Agency
U.S. Army Corps of Engineers, New England District
Performance
2026
Location
Hop Brook Lake Project Office, Middlebury, CT

Facilities repair · Asbestos abatement

Flooring removal and replacement with asbestos tile abatement at Hop Brook Lake

Removal of about 1,146 sq ft of carpet, abatement of about 423 sq ft of asbestos floor tile, and installation of about 1,266 sq ft of rigid core luxury vinyl plank plus stair treads.

What Cresco handled

  • Licensed abatement and flooring subcontractor
  • Daily air monitoring and post-abatement industrial hygiene clearance
  • 100% payment bond through CNA Surety
  • Pre-work submittals, pre-construction meeting and QC

Outcome

Abatement, clearance and new flooring handled under one bonded prime, giving the district a single point of contact for the whole scope.

03 / 10
Agency
USDA Natural Resources Conservation Service
Performance
Sep to Nov 2026
Location
NRCS storage building, Bangor, ME

Facilities repair

Roof, skylight and stair repair at the NRCS Bangor storage building

Repair of the roof, skylights, exterior stairs and entry door trim on an NRCS field storage building, awarded firm-fixed-price.

What Cresco handled

  • Selected a GAF Master Elite certified local roofing subcontractor
  • Submittals and schedule with the contracting officer
  • Site access and technical POC coordination
  • Quality oversight through closeout

Outcome

One accountable prime for the roof, skylight, stair and trim scopes, with a certified roofing installer on site.

04 / 10
Agency
U.S. Fish and Wildlife Service
Performance
Oct 2026
Location
Caddo Lake National Wildlife Refuge, Karnack, TX

Facilities repair

Roof replacement on the Caddo Lake NWR classroom trailer

Full roof replacement on the refuge classroom trailer, performed under Davis-Bacon wage requirements.

What Cresco handled

  • Local roofing subcontractor from Longview, TX
  • Site access coordinated 48 hours ahead with refuge staff
  • Certified payrolls submitted with each invoice
  • Invoicing through IPP

Outcome

A full roof replacement handled under Davis-Bacon, with certified payroll reporting on every invoice.

05 / 10
Agency
Department of Veterans Affairs
Performance
Aug to Oct 2026
Location
Captain James A. Lovell FHCC, North Chicago, IL

Equipment supply

Polarized light microscope for asbestos analysis

A brand-name or equal polarized light microscope configured for transmitted-light asbestos analysis. Cresco offered a Nikon Ci POL based system through an authorized microscopy specialist.

What Cresco handled

  • Equal-product technical match against the Leica DM2700 P spec
  • Trade Agreements Act compliant sourcing
  • Delivery, onsite installation and operator training
  • Electronic invoicing through Tungsten Network

Outcome

Installed, operational and accepted in writing by the Industrial Hygiene team on October 8, 2026.

06 / 10
Agency
National Park Service, Department of the Interior
Performance
May 12 to May 20, 2026
Location
Wawona Tunnel, Yosemite National Park, CA

Emergency electrical repair

Emergency repair of the Yosemite 2.4kV overhead line at Wawona Tunnel

Restore commercial power to Wawona Tunnel by repairing a damaged 2.4kV overhead distribution line in elevated, steep terrain.

What Cresco handled

  • De-tensioned, spliced and re-tensioned #2 solid copper conductors
  • Site-specific safety plan, fall protection and rescue readiness
  • De-energization and grounding coordination with NPS
  • Daily tailboards, photo documentation and closeout

Outcome

Completed within the performance window. Line integrity restored and the tunnel back on commercial power.

07 / 10
Agency
Indian Health Service
Performance
Jan 6 to Apr 10, 2026; completed Mar 23, 2026
Location
Yakama Service Unit, WA

Building systems modernization

Building automation system upgrade at the Yakama Service Unit

Modernize the facility Metasys BAS platform and related controls, with Johnson Controls as OEM technical subcontractor.

What Cresco handled

  • Metasys upgrade to v13.0+ and NAE to SNE controller replacement
  • BAS workstation, UPS and database migration
  • Testing, commissioning and functional verification
  • End-user training and closeout documents

Outcome

Completed March 23, 2026, more than two weeks ahead of the April 10 contract completion date.

08 / 10
Agency
USDA Agricultural Research Service
Performance
Feb 2 to Apr 30, 2026
Location
U.S. Meat Animal Research Center, Clay Center, NE

Agricultural services

Sheep shearing services for USDA research flocks

Shearing of ewes, rams and teaser rams across February and April events in support of herd health and ongoing research operations.

What Cresco handled

  • Two-person crew in February using USDA catch pens
  • Three to four person crew in April with a mobile shearing trailer
  • Scheduling with the USDA sheep manager
  • Firm-fixed-price CLIN billing per head

Outcome

Shearing events completed on schedule, supporting animal welfare and research continuity.

09 / 10
Agency
Department of Veterans Affairs
Performance
Nov 2025 to Jan 2026
Location
Chillicothe VA Medical Center, Chillicothe, OH

Equipment supply

Six steam-to-water domestic hot water heaters

Supply and delivery of six steam-to-water domestic hot water heaters to a VA medical center, meeting specified capacity, operating conditions and accessories.

What Cresco handled

  • Manufacturer and supplier coordination
  • Product and compliance submittals
  • Delivery scheduling with facility readiness
  • Startup, warranty and O&M closeout documents

Outcome

All equipment delivered to specification, coordinated with the VA contracting officer and COR through closeout.

10 / 10
Agency
National Park Service, Department of the Interior
Performance
Sep 2025
Location
Pinnacles National Park, CA

Environmental remediation

Vehicle fire hazardous materials cleanup at Pinnacles

Cleanup of fire-impacted asphalt in an active public parking area after a vehicle fire, performed by a HAZWOPER-certified subcontractor.

What Cresco handled

  • Surface decontamination with EPA-approved agents
  • Wash water recovery and DOT drum containerization
  • Licensed hazardous waste transport and disposal
  • Compliance with OSHA 29 CFR 1910.120

Outcome

Completed on schedule with no safety incidents. Cresco also flagged additional asphalt damage for follow-on restoration planning.

Need references for your file?

We will send contracting officer contacts and completed past performance questionnaires for any project on this page.